Wednesday, July 1, 2026
NEWSLETTER
Construction Intelligence
No Result
View All Result
  • News
    • Infrastructure
    • Housing
    • Safety & Wellbeing
    • Finance
    • People
    • Products
    • Architecture & Design
    • Environment
    • Awards
    • Plant & Machinery
No Result
View All Result
Construction Intelligence
No Result
View All Result

McLaren Construction completes flagship Panattoni Park Swindon development

McLaren Construction completes flagship Panattoni Park Swindon development
Share on FacebookShare on Twitter

McLaren Construction (Midlands and North) has completed the flagship industrial and logistics facility at Panattoni Park Swindon, delivering the major scheme and marking a significant milestone in the regeneration of the site.

The 545,000 sq. ft. speculative development has been delivered within a 39-week construction schedule, forming part of the wider regeneration of the former Honda manufacturing site, transforming a historic brownfield location into a high-quality logistics and employment hub for the South West.

The project was designed around a structured and collaborative delivery strategy to meet timescales, with early supply chain engagement across key packages including steel frame and cladding, to ensure all partners were aligned to the programme from inception.

The programme involved working to ensure successful on-time completion, supported by planning and consistent communication with key contractors, maintaining momentum throughout every stage of the build.

During the delivery, the scheme set a new internal benchmark for quality and sustainability achieving a BREEAM ‘Outstanding’ rating and targeting net zero upfront embodied carbon.

A range of sustainability measures were integrated without impacting the programme, including the use of cement replacement in concrete, the incorporation of recycled steel and the use of modern methods of construction such as precast concrete walling, lift cores and stair units.

The team also implemented robust environmental practices, including segregated waste streams and smart waste management, while reusing excavated materials through a carefully engineered cut-and-fill balance refined at design stage.

Alongside delivery, McLaren Construction maintained a strong focus on social value and responsible construction, and the project achieved an excellent score of 43 out of 45 in its Considerate Constructors Scheme (CCS) assessment, with a high score for community engagement environmental management, and workforce wellbeing.

The report highlighted the team’s proactive communication with stakeholders, robust environmental processes, and a strong commitment to workforce welfare including mental health support and high-quality site facilities.

McLaren Construction (Midlands and North) also supported skills development throughout the programme with apprentices across multiple trades, including five scaffolders and two electricians, as well as work placement opportunities.

The completed building offers high-specification logistics space with premium office accommodation, including a main reception area, feature link bridge and high-quality internal finishes including bespoke kitchenette areas with custom Corian worktops, glass splashbacks and feature staircases with glass balustrades.

Luke Arnold, Regional Director at McLaren Construction Midlands and North, said: “Delivering Panattoni Park Swindon is a fantastic achievement and a real credit to the entire project team. From the outset, this was an ambitious schedule, and through careful planning, strong collaboration and the commitment of our trusted supply chain, we’ve been able to complete the project on time and to an exceptional standard.

“I’d like to thank Paul, Gareth and the wider project team, along with our supply chain partners, whose dedication and coordination were critical to maintaining momentum throughout. This project demonstrates what can be achieved when the right team is aligned behind a clear programme and shared goal.”

Peter Carter Wall, Construction Director at Panattoni, said: “McLaren Construction delivered the first building on our flagship development site which is the first to implement our new interior design concept and finishes. The team took an aspiration to create something special and delivered an impressive reality that has been widely admired. It has been a pleasure working with the team, and this building stands as a showpiece achievement everyone involved should be very proud of.”

Next Post
Innovative Lightweight Solar Panels Installed at East Sussex’s Grade I Listed De La Warr Pavilion to Generate 20% of Annual Electricity Needs

Innovative Lightweight Solar Panels Installed at East Sussex’s Grade I Listed De La Warr Pavilion to Generate 20% of Annual Electricity Needs

Recommended

Construction PMI hits new low as downturn deepens

Stakeholders cut ribbon at new GMIoT base at University of Salford

Stakeholders cut ribbon at new GMIoT base at University of Salford

Popular News

  • VINCI Construction Appointed for £55m Liverpool Pall Mall Development

    VINCI Construction Appointed for £55m Liverpool Pall Mall Development

    0 shares
    Share 0 Tweet 0
  • McHale Plant Sales Takes Over Fuchs Distribution in Ireland

    0 shares
    Share 0 Tweet 0
  • Bam Secures Early Works Contract for £2.5bn Eastern Green Link 3

    0 shares
    Share 0 Tweet 0
  • Part-Completed ISG School Set for Demolition Following Structural Review

    0 shares
    Share 0 Tweet 0
  • AJC Group Secures £24m Boscombe Regeneration Contract

    0 shares
    Share 0 Tweet 0
Construction Intelligence

© 2025 Construction Intelligence

  • About
  • Advertise
  • Privacy Policy
  • Cookie Policy
  • Terms & Conditions

No Result
View All Result
  • Home

© 2025 Construction Intelligence