Thames Water has submitted its application for a Development Consent Order (DCO) to build the proposed White Horse Reservoir in Oxfordshire, marking a significant step towards delivering one of England’s largest new water storage projects.
The reservoir would be located south-west of Abingdon and is planned to become the second largest in the country once completed. It is the first of nine new reservoirs proposed for development in England as part of efforts to strengthen water supplies and improve resilience to drought.
Simon Adams, programme director at Thames Water, said: “The widespread drought this year has shown again the urgent need for new sources of water. White Horse Reservoir will provide water security for millions of families and businesses, keeping the taps flowing and unlocking economic growth across the country.
“The submission of our planning application is another significant step in delivering long-term water security for London and the South East. If approved, the reservoir means we’ll be ready to meet the challenges ahead, including increased droughts, a growing population and taking less water from the environment, which is already under pressure.”
The application will now be assessed by the Planning Inspectorate, which has 28 days to decide whether the submission is complete and meets the necessary requirements to proceed to formal examination.
If accepted, the application documents will be published on the Planning Inspectorate’s website, allowing members of the public and other interested organisations to register as interested parties and participate in the examination process.
The examination is expected to begin in spring 2027. During this stage, the Examining Authority will have up to six months to assess the proposals, seek further information and consider evidence submitted by the applicant and interested parties.
Those registered to take part will be able to contribute through written representations and comments at key stages, as well as attending public hearings where appropriate. The process will provide an opportunity for local communities, organisations and other stakeholders to examine the proposals and put forward their views before a decision is made on the application.